Overview

This Quick Resource Guide (QRG) is intended for Buyers and Procurement Officers who need to add a sub contractor for a contract in the eMaryland Marketplace Advantage (eMMA). It also shows how to enter an invoice for a sub contractor. 


If you need to create a contract in eMMA see the Procurement Officer QRGs on the Freshdesk webpage:

  • Create a Contract from Scratch
  • Create a Contract from an Awarded Solicitation

Prerequisites

  • The contract to which you are adding a sub contractor must be in Draft Status. If it is already published, then you must ask the Procurement Officer who is theResponsible Team Member for that contract to amend it and add the sub contractor.
  • If you are adding an invoice for a sub contractor, you will need an eMMA Contract number (CTR00XXXX) and an approved eMMA Purchase Order number (PO0000XXX).

    NOTE: You must be a user of DGS, DBM, DOIT, MDVA explicitly to use the sub contractor invoice function.

NOTE: For best results, use the Google Chrome browser to access eMMA.

NOTE: If you need help at any time, please reach out to the eMMA helpdesk at emma.helpdesk@maryland.gov.


Step-by-Step Instructions

NOTE: This QRG uses diagrams with specific callouts to show required and optional fields in forms. A yellow callout with a red border null indicates a required field, while yellow callouts with a black border null indicate optional fields. Letters within the callouts correspond to the explanations below the diagram.

Add a Sub contractor to a Contract

This process shows how to add a sub contractor to a contract in eMMA.

NOTE: If the sub contractor is not in eMMA you can create a profile for them in eMMA and get them registered. See the Procurement Officer QRG Create a Profile for a Vendor.

NOTE: Additional fields may display depending on your selections.
 

  1. Access eMMA at https://emma.maryland.gov and log in with your credentials.

    NOTE: Depending on your agency, you may only need to click the State SSO Login (Secure Auth) button or the MDOT SSO Login (MSAzure) button and log in with your credentials.

  2. Click the Contracts tab at the top of the homepage and select the Browse Contracts option from the drop-down menu that opens.
    The Contracts tab and the Browse Contracts option in the drop-down menu.

  3. Click on the blue hyperlink under the Contract Title or Contract ID columns.

    NOTE: The Date Status column must be Active and the Status column must be Draft.

    A contract in Draft and Active statuses.

  4. Click the +Add Sub Contractor button. The Manage Sub Contractors window opens.
    The +Add Sub Contractor button.
  5. Enter the information in the fields under the Sub Contractor Details section. A red asterisk (*) indicates a required field (*).
    A diagram of the fields for a sub-contractor in eMMA.

    1. Sub Contractor (*): Enter a term for your sub contractor to search for that vendor in eMMA. You can also click the field and click the See All option at the bottom of the drop-down menu.

      NOTE: Clicking See All opens a new window listing all vendors in eMMA. You can search for vendors or browse through the list. Click the checkbox to the left of the vendor entry and close the window to make a selection. Your selection populates in the Sub contractor field.   
    2. Program Goal Amount (*): Enter the amount for the sub-contracting goal in this field.
    3. Award Date: Enter or select the date the contract will be or was awarded in this field. 
    4. Completion Date: Enter or select the date the Contract will be complete.
    5. Description of Work: Enter a brief but detailed description of the work provided by the sub contractor.
  6. Enter the information in the fields under the Program Goals Info section. A red asterisk (*) indicates a required field.
    A diagram of the fields for the Program goals.
    1. MBE Goal? (*): Does this contract have a Minority-owned Business/Enterprise goal? Click this field and select Yes or Nofrom the drop-down menu. If you select Yes, two more fields display.
      1. MBE Sub Goal?: Does this contract have an MBE sub goal? Click this field and select Yes or No from the drop-down menu.
      2. MBE Ethnicity (*): Click this field and enter the MBE ethnicity to which the MBE Goal applies. 
    2. ACDBE Goal? (*): Does this contract have an Airport Concessions Disadvantaged Business Enterprise goal? Click this field and select Yes or No from the drop-down menu. The default selection is No.
    3. VSBE Goal? (*): Does this contract have a Veteran-Owned Small Business Enterprise goal? Click this field and select Yes or No from the drop-down menu. 
  7. Once all the required information has been entered, click the Save & Close button.
    The Save & Close button.

  8. Click the Sub Contractor tab on the left-hand side-panel to check that the Sub Contractor was properly added. Click the Edit (pencil) icon to the left of the sub contractor entry to make changes.The Sub Contractor tab and the newly added sub contractor in the contract.

Your sub contractor is now added to your contract. 

 

Instructional Video

Check out the instructional video for Entering Verified Sub contractor Payments at
https://www.gotostage.com/channel/df4ebe25df6842ae9e0c904a5e7222b3/recording/3969870ea8ae4aea834523da97e46382/watch